Project overview
The project
MAR Marine and Building Contracting L.L.C is delivering the New Quay Wall Design and Construction Works at East Wharf, Jebel Ali, for DP World under a fast-track Design & Build contract. The project replaces a 45-year-old sheet pile quay wall that had suffered over 60% section loss with a modern structure engineered for a 50-year service life in accordance with BS 6349, ASTM, CIRIA and SPM standards.
The works comprise a sheet pile quay wall with concrete infill, a ground anchor system, cast-in-situ and precast reinforced-concrete capping beam, quay furniture, dredging, revetment and apron reinstatement. MAR is responsible for engineering, procurement, construction, testing and commissioning, with the works coordinated to minimise disruption to ongoing port operations.
Delivery is coordinated with DP World’s Marine Operations, Engineering and HSE departments and the required authority approvals. Marine safety controls, daily toolbox talks, gas and lighting monitoring, and heat-stress monitoring support site operations.