Bosaso Multi Purpose Expansion Terminal Works

Phase 1 delivered a new 150m quay wall, repairs to 215m of existing quay, heavy-duty yards, a gate facility and cold-storage infrastructure.

Project details

Completed
Project reference
002
Location
Puntland, Somalia
Client
DP World
Work packages
Not provided
Designer of the project
CORINTHE
MAR executing company
MAR Marine & Building Contracting LLC
Consultant
Cullen Grummitt & Roe (CGR)
Client representative
Not provided
Contract type
Not provided
Project period
2023
Project award
Not provided
Commencement
Not provided
Expected completion
Not provided
Completion
Completed
Planned operations
Not provided
MAR project role
Not provided
Main contractor
Not provided
Subcontractor
Not provided

The project

Phase 1 expansion of Bossaso Port with a new deep-water quay, repairs to the existing quay, heavy-duty yards, gate and cold-storage facilities.

Scope of work

  • 150 LM new quay wall with 12.5 m draft
  • Repair of 215 LM existing quay
  • 3,000 sqm container-storage yard and 4,000 sqm stripping yard
  • 5,000 sqm paved gate facility
  • Cold-storage facility
  • Dredging of 1,800,000 m³ to -12 m for the approach channel, turning circle and berth pocket