Skip to content
Project reference sheet
https://marcontracting.com/projects/design-and-construction-of-new-quay-berth/
Marine

New Quay Berths Designs and Construction Hamriya

Design and construction of Mina Hamriyah New Quay Berths Phases 1 and 2, including quay wall, soil improvement, apron infrastructure and dredging.

Project details

Completed
Project reference
005
Location
Dubai, UAE
Client
DP World
Work packages
Not provided
Designer of the project
ATM & CHSS
MAR executing company
MAR Marine & Building Contracting LLC
Consultant
CHSS
Client representative
CWP Engineering
Contract type
Design & Build
Project period
2021–2024
Project award
Not provided
Commencement
Not provided
Expected completion
Not provided
Completion
February 2024
Planned operations
Not provided
MAR project role
Not provided
Main contractor
Not provided
Subcontractor
Not provided

The project

DP World UAE Region awarded MAR Marine & Building Contracting the Mina Hamriyah New Quay Berths package on 11 October 2021, with CWP Engineering acting as client representative.

Scope of work

  • Design and construction of 1,130 LM sheet-pile quay wall at -8.5 m draft with concrete capping beam
  • Soil improvement using vibro-compaction and rapid-impact compaction
  • Design and construction of a 100,000 sqm apron with infrastructure, pavement, MEP and service blocks
  • Dredging of 1,000,000 m³ to -9.8 m

Related projects