Al Rughaylat Port — Phases 1, 2 and 3 (Packages A, B, C and D)

Marine and landside infrastructure at Al Rughaylat Port in Fujairah, spanning breakwaters, dredging, a precast-block quay wall, a Ro-Ro ramp and harbour facilities.

Project details

Ongoing
Project reference
034 · 041
Location
Al Rughaylat Port, Fujairah, on the east coast of the UAE
Client
Port of Fujairah
Work packages
A, B, C and D
Designer of the project
MUC Engineering
MAR executing company
MAR Marine & Building Contracting LLC
Consultant
MUC Engineering
Client representative
Not provided
Contract type
Not provided
Project period
2024–present
Project award
4 December 2024
Commencement
4 December 2024
Expected completion
Not provided
Completion
Ongoing
Planned operations
Not provided
MAR project role
Not provided
Main contractor
Not provided
Subcontractor
Not provided

The project

Al Rughaylat Port development across Phases 1, 2 and 3, encompassing Packages A, B, C and D in Fujairah, on the east coast of the United Arab Emirates. The supplied project brief describes Package A for breakwaters and revetments, Package B for dredging, and Package C for the quay wall, Ro-Ro ramp, roadworks and dhow inspection jetty. The works also include crown walls, interlock paving, precast kerbs, perimeter fencing, marine furniture and aids to navigation.

Scope of work

  • Package A: construction of the 910 m southern breakwater, 155 m northern breakwater and associated revetments
  • Package B: 839,289 m³ of dredging to the design level of -7.00 m FHD
  • Package C: construction of the 856 m precast-block quay wall, a 16 × 48 m Ro-Ro ramp, roadworks and dhow inspection jetty
  • Construction of 1,150 m of crown walls at the breakwaters
  • 85,787 m² of interlock pavement, 12,000 m of precast kerbs and 2,240 m of chain-link fencing
  • Dhow inspection jetty and pontoon, including an aluminium gangway
  • Installation of 213 AN-fenders and 48 bollards rated at 25 tonnes
  • Installation of two land bollards rated at 30 tonnes and eight land bollards rated at 50 tonnes
  • Installation of 24 ladders and 48 mooring rings
  • Installation of eight aids to navigation