Medco tank farm loading / off loading sea pipelines 2012

Location: BEIRUT-LEBANON
Client: MEDCO S.A.R.L
Main Contractor: MAR GROUP
Consultant:

Rafic Khoury Consultancy

Date: 2017-07-04
  • Ballast installation for quay wall
  • Precast quay wall installation consisting of 120 tons blocks @ 18m depth
  • Backfilling behind walls
  • Geotextile fabric installation
  • Reinforced concrete coping casting
  • Providing offshore & onshore equipment for steel pile driving & vibro compaction.
  • Sheet pile driving
  • Tubular piles shop & field splicing and welding

Beirut Port-Quay 16 Extension – Construction of 600m Quay Wall at 18m depth

Share: