CIMENTERIE NATIONAL S.A.L SEA WATER INTAKE PIPELINE & PUMPING STATION 2009

Sea Pipelines Installation

Share

  • Location:

    CHEKKA , LEBANON

  • Client:

    CIMENTERIE NATIONAL S.A.L

  • Main Contractor:

    MAR Group

  • Consultant:

    LIBAN CONSULT S.A.R.L

  • Date

    2017-07-04

Description

Cooling Plant For Power Generators – Design Build Package For The Cooling Plant Intake Pipeline, Channel And Pumping Station Basin

Project Specifics

  • Sea water intake pipeline of 1200mm diameter
  • Offshore dredging of intake pipeline channel in hard rock
  • Installation of ballast layer
  • Casting and installation of precast concrete weight blocks with protective epdm rubber layer
  • Installation of 1200mm grp pipe
  • Backfilling with approved anti scouring material and reinstatement of existing sea bed
  • Supply and installation of aspiration chamber
  • Excavation and construction of 5000 m3 water basin in hard rock
  • Construction of cylindrical concrete walls, sand traps and covers