DORALEH OIL TERMINAL REHABILITATION OF PIERS & DOLPHINS 2012-2013

Location /DJIBOUTI, DJIBOUTI
Client /DP WORLD
Main Contractor /HOMAN GROUP
Consultant /TECHNITAL
Description
<<DORALEH OIL TERMINAL- REHABILITATION AND MAINTENANCE>>

Project Specifics

    Marine growth cleaning of existing tubular steel piles starting from Level -20m
    Removal and replacement of 10 nos. Jetty access ladders
    Maintenance of 13 nos. Super cell fender systems 5nos. (Suc1600h/re-s)& 8Nos. (Syc 1250 h/rs-s) including removal of fender frontal frame, sand Blasting, painting and replacement of friction pads in addition to replacement Of all fixing bolts system
    Supply and installation of new (suc1600h/re-s) super cell fender systems
    Supply and welding of zinc anodes
    Cleaning using hydro blasting system
    Concrete repair and application of concrete protection system on all existing concrete deck and underdeck
    Design, supply and installation of temporary scaffolding system as a standing platform to perform the underdeck repair works
    Sand blasting for all steel structures for access jetty, platform and mooring dolphins including supply and application of epoxy painting with all related scaffolding required for serviceability
    Underwater hydro blasting for all piles and steel structures and specifically on The splash zones including application of special underwater epoxy protection coating system
    Complete maintenance of existing mooring hooks