AL JABALYAN CENTRAL PROCESS FACILITY STEEL STORAGE TANKS 2006

Location /AL JABALYAN, SUDAN
Client /JAB – CPF 1
Main Contractor /RANHILL-PETRONEED
Consultant /RANHILL-PETRONEED
Description
<<Construction of 11 Steel Tanks Including Piping Network & Accersories>>

Project Specifics

    Fabrication, erection, welding and testing of 11 x steel tanks used for storage of water and petroleum products in addition to special tanks for crude oil process system using steam
    Fabrication and installation of all related accessories, insulation, internal and external piping networks, heating systems, sand blasting and painting in addition to testing according to international standards and codes.

Date:

July 4, 2017

Category:

Steel Selective